36"12.0 ft wall16" on centre
ft
in

From your span table

Opening type

16" on centre

20studs

Field studs

8

King + jack

4

Top plate

24.0 ft

The count

Field studs10 on-centre marks along the wall, less the ones an opening swallows
8
Corner studs2 corners at 3 studs each
6
King studsFull height, one each side of every opening
2
Jack studsUnder the header — you set how many a side
2
CripplesAbove the header only
2
Bottom plateSingle
12.0 ft
Top plateDoubled
24.0 ft

Before you cut

  • Openings fit inside the wall — passes36.0" of openings in a 144.0" wall, leaving room for king studs on every side.
Check this first
0123456

Put a tape on the printed ruler. If it does not read exactly 6 inches, the print was scaled — set the print dialog to 100% or “Actual size” and print it again. Do not cut wood from a template that failed this.

One 16" on-centre pitch — piece 1 of 3, 0" to 5 5/16" across the strip
0

Mark a story pole at these two ticks, then step it down the wall for every field stud. Trim on the orange line and butt this piece to the next one — the marks either side of the join have to line up before you drill anything.

One 16" on-centre pitch — piece 2 of 3, 5 5/16" to 10 11/16" across the strip

Mark a story pole at these two ticks, then step it down the wall for every field stud. Trim on the orange line and butt this piece to the next one — the marks either side of the join have to line up before you drill anything.

One 16" on-centre pitch — piece 3 of 3, 10 11/16" to 16" across the strip
16"

Mark a story pole at these two ticks, then step it down the wall for every field stud. Trim on the orange line and butt this piece to the next one — the marks either side of the join have to line up before you drill anything.

This does not size the header

How many jack studs a header needs depends on its span and the load stacked above it — species, grade, snow load and how much of the building bears on that wall all matter, and getting it wrong is a structural mistake rather than a cosmetic one. This calculator counts the studs a jack-stud decision requires; check a span table or an engineer for the decision itself, then come back and set the count above.